| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100212 | Zocalo en arenon chino lavado No. 1 y 2 h=0.60m | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENON | Arenon chino N° 1 25 kg | un | 45.000000 | $11,500.00 | $517,500.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.200000 | $21,704.00 | $4,340.80 |
| MOLD01 | Moldura dilatacion 1x1 | ml | 2.000000 | $1,683.00 | $3,366.00 |
| Suma de Material | $525,206.80 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.068750 | $121,896.00 | $8,380.35 |
| Suma de Mano de Obra | $8,380.35 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $533,587.15 |