| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100201 | Guardaescoba en arenón chino lavado No. 1 y 2 | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENON | Arenon chino N° 1 25 kg | un | 4.210000 | $11,500.00 | $48,415.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.010420 | $21,704.00 | $226.16 |
| MOLD01 | Moldura dilatacion 1x1 | ml | 1.000000 | $1,683.00 | $1,683.00 |
| Suma de Material | $50,324.16 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.031250 | $121,896.00 | $3,809.25 |
| Suma de Mano de Obra | $3,809.25 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $54,133.41 |