| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070108 | Sillar prefabricado M20 | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SIL20 | Sillar prefabricado 22x6 | ml | 1.030000 | $18,908.00 | $19,475.24 |
| Suma de Material | $19,475.24 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla Mampostería | jor | 0.035620 | $116,803.00 | $4,160.52 |
| Suma de Mano de Obra | $4,160.52 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.230000 | $1,000.00 | $230.00 |
| TRANS | Transporte de materiales | gl | 0.300000 | $1,000.00 | $300.00 |
| Suma de Auxiliar | $530.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.050000 | $285,872.00 | $14,293.60 |
| Suma de Concepto | $14,293.60 | ||||
| Costo Directo | $38,459.36 |