| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 140301 | Acometida television | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOPVCO30 | Tubo pvc-conduit 1" - Pavco | ml | 1.000000 | $8,739.00 | $8,739.00 |
| CABLECOA90 | Cable coaxial RG-6/U 18 90% awg | ml | 1.000000 | $848.00 | $848.00 |
| CURPVC15 | Curva pvc conduit 1 | un | 0.200000 | $1,812.00 | $362.40 |
| VARIO | Varios electricos | un | 0.232000 | $1,318.00 | $305.78 |
| Suma de Material | $10,255.18 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.039847 | $116,803.00 | $4,654.25 |
| Suma de Mano de Obra | $4,654.25 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $14,909.43 |