| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110602 | Caja 30 x 30 | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.250000 | $21,704.00 | $5,426.00 |
| HERRACAJA01 | Herraje caja inspeccion 30*30 | un | 1.000000 | $29,582.00 | $29,582.00 |
| Suma de Material | $35,008.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.147059 | $115,595.00 | $16,999.29 |
| Suma de Mano de Obra | $16,999.29 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Concepto | |||||
| 050105 | Formaleta caja 30*30. | un | 1.000000 | $12,434.00 | $12,434.00 |
| 050203 | Concreto 3000 psi en obra | m3 | 0.153000 | $294,870.00 | $45,115.11 |
| Suma de Concepto | $57,549.11 | ||||
| Costo Directo | $109,556.40 |