| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 131002 | Caja 60x60 RS3-015 EPM | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRITU02 | Triturado 3/4" | m3 | 0.018900 | $38,280.00 | $723.49 |
| HERRA51 | Herraje 60x60 RS3-015 EPM | un | 1.000000 | $106,166.00 | $106,166.00 |
| Suma de Material | $106,889.49 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.568680 | $115,595.00 | $65,736.56 |
| Suma de Mano de Obra | $65,736.56 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.066000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRZAGR10 | Transporte triturado | m3 | 0.018900 | $19,800.00 | $374.22 |
| TRLOC | Transporte local | m3 | 0.037800 | $5,000.00 | $189.00 |
| Suma de Auxiliar | $563.22 | ||||
| Concepto | |||||
| 050104 | Formaleta caja inspeccion 60x60. | un | 1.000000 | $12,434.00 | $12,434.00 |
| 050202 | Concreto 2500 psi en obra | m3 | 0.037800 | $280,450.00 | $10,601.01 |
| 070106 | Muro 15 bloque concreto | m2 | 1.522500 | $51,569.00 | $78,513.80 |
| 050216 | Mortero 1:4 de revoque | m3 | 0.007000 | $276,729.00 | $1,937.10 |
| 040206 | Refuerzo de 60.000 psi | kg | 3.200000 | $2,910.00 | $9,312.00 |
| Suma de Concepto | $112,797.92 | ||||
| Costo Directo | $285,987.19 |