| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010202 | Campamento en Teleras | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC2500 | Concreto 2500 psi premezclado (agregado 3/4) | m3 | 0.071000 | $270,093.00 | $19,176.60 |
| PIEDRAE2 | Piedra de entresuelo (sum + transp) | m3 | 0.200000 | $66,125.00 | $13,225.00 |
| RECEBO | Recebo comun | m3 | 0.050000 | $38,280.00 | $1,914.00 |
| MALLAPOLLO | Malla pollo | m2 | 1.200000 | $1,204.00 | $1,444.80 |
| TABLA | Tabla madera comun | un | 0.870000 | $6,090.00 | $5,298.30 |
| CAN05 | Can sin zunchar 3.5 cm x 19 cm en madera comun | un | 0.377000 | $10,154.00 | $3,828.06 |
| LARGUCOMUN | Larguero madera comun 4cmx8cmx2.80m | un | 1.645000 | $4,872.00 | $8,014.44 |
| TEL45 | Telera de 45*135 | un | 0.726000 | $7,500.00 | $5,445.00 |
| TEL90 | Telera de 90*135 | un | 1.035000 | $14,500.00 | $15,007.50 |
| BISAGRCOM3 | Bisagra comun 3" | un | 0.097000 | $2,610.00 | $253.17 |
| TELAPOL | Tela polipropileno | ml | 0.555000 | $1,555.00 | $863.03 |
| TORNIG20 | Tornillo goloso 1x6" | un | 0.100000 | $29.00 | $2.90 |
| ALAMBRCOB08 | Alambre cobre desnudo 8 awg | ml | 1.742000 | $3,038.00 | $5,292.20 |
| ALAMBRCOB04 | Alambre cobre desnudo 4 awg | ml | 1.142000 | $7,673.00 | $8,762.57 |
| CABLETEL | Cable telefax | ml | 0.774000 | $1,234.00 | $955.12 |
| TOMAD03 | Toma doble Americana LEVINTON | un | 0.039000 | $2,184.00 | $85.18 |
| SUICHE01 | Suiche sencillo | un | 0.068000 | $3,192.00 | $217.06 |
| TOMATEL02 | Toma telefono doble RJ11 PRM440102 | un | 0.029000 | $12,094.00 | $350.73 |
| CINTAS33 | Cinta sctch 33 19mmx8m | un | 0.080000 | $13,952.00 | $1,116.16 |
| LAMP35 | Lampara 2x96 w de tubo | un | 0.019000 | $50,810.00 | $965.39 |
| TEJAZON | Teja zinc ondulada calibre 34 | un | 0.716000 | $15,950.00 | $11,420.20 |
| AMARR10 | Amarres tejas | un | 5.709000 | $150.00 | $856.35 |
| CLAVOSCOM1-3 | Clavos comunes 1½ a 3½" | lb | 0.410800 | $1,364.00 | $560.33 |
| OTRMA | Otros materiales | gl | 0.100000 | $1,000.00 | $100.00 |
| Suma de Material | $105,154.06 | ||||
| Mano de Obra | |||||
| ZCUADMT | Cuadrilla Mvto de tierra | jor | 0.055500 | $107,037.00 | $5,940.55 |
| ZCUADEST | Cuadrilla Estructura | jor | 0.069800 | $115,595.00 | $8,068.53 |
| ZCUADCUB | Cuadrilla Cubierta | jor | 0.023600 | $121,896.00 | $2,876.75 |
| ZCUADCAR | Cuadrilla Carpinteria | jor | 0.007400 | $121,896.00 | $902.03 |
| ZCUADINS | Cuadrilla Instalaciones | jor | 0.049900 | $116,803.00 | $5,828.47 |
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.032100 | $116,803.00 | $3,749.38 |
| Suma de Mano de Obra | $27,365.71 | ||||
| Auxiliar | |||||
| TRZAGR20 | Transporte pétreos | m3 | 0.050000 | $20,571.00 | $1,028.55 |
| Suma de Auxiliar | $1,028.55 | ||||
| Concepto | |||||
| 020412 | Transporte piedra entresuelo | m3 | 0.200000 | $19,800.00 | $3,960.00 |
| Suma de Concepto | $3,960.00 | ||||
| Costo Directo | $137,508.32 |