| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110502 | Material seleccionado para filtro | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRITU03 | Triturado 1½" | m3 | 1.150000 | $38,280.00 | $44,022.00 |
| Suma de Material | $44,022.00 | ||||
| Mano de Obra | |||||
| ZCUADIMP | Cuadrilla Impermeabilizaciones | jor | 0.042146 | $124,054.00 | $5,228.38 |
| Suma de Mano de Obra | $5,228.38 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRZAGR10 | Transporte triturado | m3 | 1.150000 | $19,800.00 | $22,770.00 |
| TRLOC | Transporte local | m3 | 1.150000 | $5,000.00 | $5,750.00 |
| Suma de Auxiliar | $28,520.00 | ||||
| Costo Directo | $77,770.38 |