| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130805 | Tablero monofasico 4 circuitos | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABLEROMON10 | Tablero monofasico 4 ctos | un | 1.000000 | $22,100.00 | $22,100.00 |
| BRK | Breaker westing | un | 2.000000 | $3,501.00 | $7,002.00 |
| VARIO | Varios electricos | un | 0.500000 | $1,318.00 | $659.00 |
| Suma de Material | $29,761.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.153257 | $116,803.00 | $17,900.88 |
| Suma de Mano de Obra | $17,900.88 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.000000 | $1,000.00 | $1,000.00 |
| Suma de Auxiliar | $1,000.00 | ||||
| Costo Directo | $48,661.88 |