| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070111 | Sobrecimiento bloque 10 | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQR083P-10-20 | Bloque R8 3P no estructural 10x20x40 | un | 13.125000 | $1,120.00 | $14,700.00 |
| Suma de Material | $14,700.00 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla Mampostería | jor | 0.066780 | $116,803.00 | $7,800.10 |
| Suma de Mano de Obra | $7,800.10 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.300000 | $1,000.00 | $300.00 |
| Suma de Auxiliar | $300.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.016000 | $285,872.00 | $4,573.95 |
| 050201 | Concreto 2000 psi en obra | m3 | 0.050000 | $261,470.00 | $13,073.50 |
| Suma de Concepto | $17,647.45 | ||||
| Costo Directo | $40,447.56 |