| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090301 | Base asfaltica | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BASEASF01 | Base asfaltica al 3% (T max 1") (norma Area metropolitana) | ton | 1.350000 | $153,340.00 | $207,009.00 |
| Suma de Material | $207,009.00 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.421456 | $118,357.00 | $49,882.27 |
| Suma de Mano de Obra | $49,882.27 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| COMPACT25 | Compactador vibratorio | hr | 0.066670 | $100,000.00 | $6,667.00 |
| FINISH | Finisher | hr | 0.066670 | $82,000.00 | $5,466.94 |
| Suma de Equipo | $12,133.94 | ||||
| Concepto | |||||
| 090409 | Riego de liga | m2 | 13.330000 | $710.00 | $9,464.30 |
| Suma de Concepto | $9,464.30 | ||||
| Costo Directo | $278,489.51 |