| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110616 | Realce cuello para manhole | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CUELLO02 | Cuello pref manhole | un | 1.000000 | $141,633.00 | $141,633.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.200000 | $21,704.00 | $4,340.80 |
| Suma de Material | $145,973.80 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.235294 | $115,595.00 | $27,198.81 |
| Suma de Mano de Obra | $27,198.81 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| COMPRES01 | Compresor un martillo (alquiler) | hr | 0.066670 | $58,000.00 | $3,866.86 |
| Suma de Equipo | $3,866.86 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 2.300000 | $1,000.00 | $2,300.00 |
| TRMAT | Transporte materiales | glo | 7.500000 | $1,000.00 | $7,500.00 |
| Suma de Auxiliar | $9,800.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.055000 | $285,872.00 | $15,722.96 |
| 020402 | Cargue (Paleros)-transp-botada. | m3 | 1.000000 | $27,048.00 | $27,048.00 |
| Suma de Concepto | $42,770.96 | ||||
| Costo Directo | $229,610.43 |