| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090121 | Piso en grano #2 | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GRANOR | Grano rioclaro 1-2 (25 Kg) | kg | 2.000000 | $410.00 | $820.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 0.180000 | $21,704.00 | $3,906.72 |
| ESTOP | Estopa | kg | 0.050000 | $4,360.00 | $218.00 |
| Suma de Material | $4,944.72 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.082500 | $121,896.00 | $10,056.42 |
| Suma de Mano de Obra | $10,056.42 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.414000 | $1,000.00 | $414.00 |
| Suma de Auxiliar | $414.00 | ||||
| Costo Directo | $15,415.14 |