| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070107 | Muro 20 bloque concreto | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQCON20A | Bloque concreto 20x20x40 | un | 13.125000 | $2,200.00 | $28,875.00 |
| Suma de Material | $28,875.00 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla MamposterÃa | jor | 0.072340 | $116,803.00 | $8,449.53 |
| Suma de Mano de Obra | $8,449.53 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 0.243070 | $4,365.00 | $1,061.00 |
| Suma de Equipo | $1,061.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.276000 | $1,000.00 | $276.00 |
| TRANS | Transporte de materiales | gl | 1.200000 | $1,000.00 | $1,200.00 |
| Suma de Auxiliar | $1,476.00 | ||||
| Concepto | |||||
| 020343 | Cortadora de ladrillo / operador | dia | 0.031580 | $87,620.00 | $2,767.04 |
| 050209 | Mortero 1: 4 de pega | m3 | 0.040000 | $285,872.00 | $11,434.88 |
| Suma de Concepto | $14,201.92 | ||||
| Costo Directo | $54,063.45 |