| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110615 | Realce cajas | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| HERRACAJA01 | Herraje caja inspeccion 30*30 | un | 0.800000 | $29,582.00 | $23,665.60 |
| Suma de Material | $23,665.60 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.147059 | $115,595.00 | $16,999.29 |
| Suma de Mano de Obra | $16,999.29 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMALETA | Formaleta | gl | 10.000000 | $1,000.00 | $10,000.00 |
| Suma de Equipo | $10,000.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 2.300000 | $1,000.00 | $2,300.00 |
| Suma de Auxiliar | $2,300.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.020000 | $294,870.00 | $5,897.40 |
| Suma de Concepto | $5,897.40 | ||||
| Costo Directo | $58,862.29 |