| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070215 | Muro ladrillo bocadillo | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LADRBN6X12X25 | Ladrillo bocadillo natural 6x12x25 | un | 67.000000 | $447.00 | $29,949.00 |
| Suma de Material | $29,949.00 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla MamposterÃa | jor | 0.147059 | $116,803.00 | $17,176.93 |
| Suma de Mano de Obra | $17,176.93 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| OBRAFALSA | Obra falsa (alquiler) | dÃa | 0.121540 | $4,365.00 | $530.52 |
| CORTALADR | Cortadora de ladrillo / disco y operador | dÃa | 0.066670 | $87,620.00 | $5,841.63 |
| Suma de Equipo | $6,372.15 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 1.000000 | $1,000.00 | $1,000.00 |
| TRMAT | Transporte materiales | glo | 1.500000 | $1,000.00 | $1,500.00 |
| Suma de Auxiliar | $2,500.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.054000 | $285,872.00 | $15,437.09 |
| Suma de Concepto | $15,437.09 | ||||
| Costo Directo | $71,435.17 |