| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110617 | Realce sumidero | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJASB | Reja sumidero T-B (.50x.80) | un | 1.000000 | $218,915.00 | $218,915.00 |
| Suma de Material | $218,915.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.220588 | $115,595.00 | $25,498.87 |
| Suma de Mano de Obra | $25,498.87 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMALETA | Formaleta | gl | 10.000000 | $1,000.00 | $10,000.00 |
| Suma de Equipo | $10,000.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 1.600000 | $1,000.00 | $1,600.00 |
| Suma de Auxiliar | $1,600.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.210000 | $294,870.00 | $61,922.70 |
| 020402 | Cargue (Paleros)-transp-botada. | m3 | 0.160000 | $27,048.00 | $4,327.68 |
| Suma de Concepto | $66,250.38 | ||||
| Costo Directo | $322,264.25 |