| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130213 | Canalizacion 2#4/0+1#2/0 cu-thw pvc 3" | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOPVDB03 | Tubo pvc-db 3" - Pavco | ml | 1.000000 | $10,420.00 | $10,420.00 |
| CABLECOBT02/0 | Cable cobre THHN/THWN 2/0 awg | ml | 1.000000 | $26,488.00 | $26,488.00 |
| CABLECOBT04/0 | Cable cobre THHN/THWN 4/0 awg | ml | 2.000000 | $41,505.00 | $83,010.00 |
| Suma de Material | $119,918.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.127714 | $116,803.00 | $14,917.38 |
| Suma de Mano de Obra | $14,917.38 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $134,835.38 |