| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100213 | Zocalo en mortero de cemento h=0.60m | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MOLD01 | Moldura dilatacion 1x1 | ml | 2.250000 | $1,683.00 | $3,786.75 |
| Suma de Material | $3,786.75 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.031250 | $121,896.00 | $3,809.25 |
| Suma de Mano de Obra | $3,809.25 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Concepto | |||||
| 050216 | Mortero 1:4 de revoque | m3 | 0.010000 | $276,729.00 | $2,767.29 |
| Suma de Concepto | $2,767.29 | ||||
| Costo Directo | $10,363.29 |