| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050613 | Reja piso pref 80*80 tipo metro | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJAPI | Reja piso concreto 80*80 | un | 1.000000 | $35,051.00 | $35,051.00 |
| Suma de Material | $35,051.00 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.117601 | $115,595.00 | $13,594.09 |
| Suma de Mano de Obra | $13,594.09 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.000000 | $1,000.00 | $1,000.00 |
| Suma de Auxiliar | $1,000.00 | ||||
| Costo Directo | $49,645.09 |