| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130907 | Transformador 3F - 45 kva RA2-0 | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRANSF45 | Transformador 3F 34.5KV 220/127V 45 KVA | un | 1.000000 | $30,605,271.00 | $30,605,271.00 |
| VARCOOP1 | Varilla cooperwell 1"x=2.40m | un | 1.000000 | $36,400.00 | $36,400.00 |
| TORNIEM02 | Tornillo ensamble 5/16 | un | 3.000000 | $46.00 | $138.00 |
| CONECOMP | Conector comp 1/0 | un | 3.000000 | $3,119.00 | $9,357.00 |
| CRUC2 | Cruceta galvanizada 2.4mx3"x1/4" | un | 1.000000 | $105,989.00 | $105,989.00 |
| TIRA2 | Tiranta ANG-1215-N018-MN | un | 1.000000 | $15,469.00 | $15,469.00 |
| ALAMBRCOB10 | Alambre cobre desnudo 10 awg | ml | 25.000000 | $1,733.00 | $43,325.00 |
| ALAMBRCOB12 | Alambre cobre desnudo 12 awg | ml | 17.000000 | $1,106.00 | $18,802.00 |
| CORTAC1 | Cortacircuitos prim 100A-15KV Celsa | un | 1.000000 | $221,312.00 | $221,312.00 |
| PARAR | Pararrayos OB 10KA-10KVPDV-100 | un | 1.000000 | $92,960.00 | $92,960.00 |
| FUSIB10 | Fusible tipo H-K | un | 1.000000 | $2,373.00 | $2,373.00 |
| ESTRI | Estribo | un | 1.000000 | $3,287.00 | $3,287.00 |
| VARIO | Varios electricos | un | 2.000000 | $1,318.00 | $2,636.00 |
| Suma de Material | $31,157,319.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.893900 | $116,803.00 | $104,410.20 |
| Suma de Mano de Obra | $104,410.20 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 20.000000 | $1,000.00 | $20,000.00 |
| Suma de Auxiliar | $20,000.00 | ||||
| Costo Directo | $31,281,729.20 |