| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110207 | Tubo concreto 16 uec. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONCRE17 | Tubo concreto sin refuerzo D=16" L=1.2m cl2 | ml | 1.030000 | $78,494.00 | $80,848.82 |
| ENSAYOT18 | Ensayo de tuberia | gl | 1.000000 | $1,259.00 | $1,259.00 |
| Suma de Material | $82,107.82 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.114943 | $118,357.00 | $13,604.31 |
| Suma de Mano de Obra | $13,604.31 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.043480 | $70,000.00 | $3,043.60 |
| Suma de Equipo | $3,043.60 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.890000 | $1,000.00 | $1,890.00 |
| Suma de Auxiliar | $1,890.00 | ||||
| Costo Directo | $100,645.73 |