| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050802 | Losa aligerada caseton no recuperable. e=0.35m | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC3000 | Concreto 3000 psi premezclado (agregado 3/4) | m3 | 0.187000 | $287,014.00 | $53,671.62 |
| SERBOM | Servicio de bombeo | m3 | 0.187000 | $24,088.00 | $4,504.46 |
| CASETON15 | Caseton icopor (perdido) | m2 | 1.050000 | $15,162.00 | $15,920.10 |
| MALLAPOLLO | Malla pollo | m2 | 1.200000 | $1,204.00 | $1,444.80 |
| DIST1 | Distanciador de refuerzo | un | 4.000000 | $399.00 | $1,596.00 |
| Suma de Material | $77,136.97 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.121460 | $115,595.00 | $14,040.17 |
| Suma de Mano de Obra | $14,040.17 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR00 | Vibrador de concreto | día | 0.072240 | $72,672.00 | $5,249.83 |
| Suma de Equipo | $5,249.83 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.187000 | $5,000.00 | $935.00 |
| Suma de Auxiliar | $935.00 | ||||
| Concepto | |||||
| 050102 | Formaleta borde de losa | ml | 0.800000 | $4,361.00 | $3,488.80 |
| 050116 | Formaleta fondo de losa | m2 | 1.000000 | $7,171.00 | $7,171.00 |
| 050128 | Tacado doble para losas | m2 | 1.000000 | $12,575.00 | $12,575.00 |
| 030104 | Ensayos de cilindros a compresion | un | 0.040000 | $60,406.00 | $2,416.24 |
| 030105 | Prueba de asentamiento | un | 0.040000 | $5,462.00 | $218.48 |
| 030102 | Diseño de mezclas de concreto | un | 0.050000 | $507,216.00 | $25,360.80 |
| Suma de Concepto | $51,230.32 | ||||
| Costo Directo | $148,592.29 |