| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010549 | Traslado de transformador monofasico | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VARCOOP1 | Varilla cooperwell 1"x=2.40m | un | 1.000000 | $36,400.00 | $36,400.00 |
| PARAR | Pararrayos OB 10KA-10KVPDV-100 | un | 1.000000 | $92,960.00 | $92,960.00 |
| ALAMBRCOB12 | Alambre cobre desnudo 12 awg | ml | 13.000000 | $1,106.00 | $14,378.00 |
| TORNIEM02 | Tornillo ensamble 5/16 | un | 3.000000 | $46.00 | $138.00 |
| CONECTR10 | Conector transversal universal 4/0 | un | 1.000000 | $24,380.00 | $24,380.00 |
| VARIO | Varios electricos | un | 3.480000 | $1,318.00 | $4,586.64 |
| Suma de Material | $172,842.64 | ||||
| Mano de Obra | |||||
| ZCUADRET | Cuadrilla Retiros | jor | 4.055944 | $107,037.00 | $434,136.08 |
| Suma de Mano de Obra | $434,136.08 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMATB | Transporte materiales a la bodega | glo | 20.000000 | $1,000.00 | $20,000.00 |
| Suma de Auxiliar | $20,000.00 | ||||
| Costo Directo | $626,978.72 |