| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040101 | Atraque en concreto | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.216270 | $115,595.00 | $24,999.73 |
| Suma de Mano de Obra | $24,999.73 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMALETA | Formaleta | gl | 5.000000 | $1,000.00 | $5,000.00 |
| Suma de Equipo | $5,000.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 1.050000 | $5,000.00 | $5,250.00 |
| Suma de Auxiliar | $5,250.00 | ||||
| Concepto | |||||
| 050202 | Concreto 2500 psi en obra | m3 | 1.050000 | $280,450.00 | $294,472.50 |
| Suma de Concepto | $294,472.50 | ||||
| Costo Directo | $329,722.23 |