| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 131001 | Caja 50x50 RS3-016 EPM | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRITU02 | Triturado 3/4" | m3 | 0.013125 | $38,280.00 | $502.43 |
| HERRA50 | Herraje 50x50 RS3-016 EPM | un | 1.000000 | $94,371.00 | $94,371.00 |
| Suma de Material | $94,873.43 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.516980 | $115,595.00 | $59,760.30 |
| Suma de Mano de Obra | $59,760.30 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.066000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRZAGR10 | Transporte triturado | m3 | 0.013120 | $19,800.00 | $259.78 |
| TRLOC | Transporte local | m3 | 0.304500 | $5,000.00 | $1,522.50 |
| Suma de Auxiliar | $1,782.28 | ||||
| Concepto | |||||
| 050104 | Formaleta caja inspeccion 60x60. | un | 1.000000 | $12,434.00 | $12,434.00 |
| 050202 | Concreto 2500 psi en obra | m3 | 0.026250 | $280,450.00 | $7,361.81 |
| 070106 | Muro 15 bloque concreto | m2 | 1.050000 | $51,569.00 | $54,147.45 |
| 050216 | Mortero 1:4 de revoque | m3 | 0.007000 | $276,729.00 | $1,937.10 |
| 040206 | Refuerzo de 60.000 psi | kg | 3.000000 | $2,910.00 | $8,730.00 |
| Suma de Concepto | $84,610.37 | ||||
| Costo Directo | $241,026.37 |