| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 120205 | Tubo pvc-p ½" | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOPVP01 | Tubo pvc rde 9 de ½" - Pavco | ml | 1.050000 | $2,559.00 | $2,686.95 |
| UNIONPVP01 | Union pvc-p ½" - Pavco | un | 0.166670 | $280.00 | $46.67 |
| CODOPVP01 | Codo pvc-p ½ x 90 | un | 0.300000 | $421.00 | $126.30 |
| TEEPV01 | Tee pvc-p ½ - Pavco | un | 0.300000 | $578.00 | $173.40 |
| LIMPIADOR1 | Limpiador pvc (¼) | un | 0.015000 | $24,592.00 | $368.88 |
| SOLDPVC02 | Soldadura pvc (¼) - Pavco | un | 0.015000 | $50,808.00 | $762.12 |
| Suma de Material | $4,164.32 | ||||
| Mano de Obra | |||||
| ZCUADFON | Cuadrilla FontanerÃa | jor | 0.012280 | $116,803.00 | $1,434.34 |
| Suma de Mano de Obra | $1,434.34 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $5,598.66 |