| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 140213 | Curva pvc-db 2" | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CURPVC20 | Curva pvc conduit 2 | un | 1.000000 | $8,525.00 | $8,525.00 |
| VARIO | Varios electricos | un | 0.500000 | $1,318.00 | $659.00 |
| SOLDPVC02 | Soldadura pvc (¼) - Pavco | un | 0.020000 | $50,808.00 | $1,016.16 |
| Suma de Material | $10,200.16 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.071520 | $116,803.00 | $8,353.75 |
| Suma de Mano de Obra | $8,353.75 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 0.500000 | $1,000.00 | $500.00 |
| Suma de Auxiliar | $500.00 | ||||
| Costo Directo | $19,053.91 |