| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 090404 | Losa maciza en concreto de 21 Mpa e=20 cm | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.093583 | $115,595.00 | $10,817.73 |
| Suma de Mano de Obra | $10,817.73 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 0.220000 | $5,000.00 | $1,100.00 |
| Suma de Auxiliar | $1,100.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.220000 | $294,870.00 | $64,871.40 |
| 050118 | Formaleta losa | m2 | 1.000000 | $16,319.00 | $16,319.00 |
| Suma de Concepto | $81,190.40 | ||||
| Costo Directo | $93,108.13 |