| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050602 | Bancas en concreto 40x40 abujardado | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BANCAGR40GRIS01 | Banca 40x40x40 grano gris abuzardado | un | 1.000000 | $131,081.00 | $131,081.00 |
| SIKAD23 | Sikadur-32 primer (3 kg) - Sika | kg | 0.110000 | $47,560.00 | $5,231.60 |
| Suma de Material | $136,312.60 | ||||
| Mano de Obra | |||||
| ZCUADINS | Cuadrilla Instalaciones | jor | 0.306890 | $116,803.00 | $35,845.67 |
| Suma de Mano de Obra | $35,845.67 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 5.000000 | $1,000.00 | $5,000.00 |
| Suma de Auxiliar | $5,000.00 | ||||
| Concepto | |||||
| 050202 | Concreto 2500 psi en obra | m3 | 0.028350 | $280,450.00 | $7,950.76 |
| Suma de Concepto | $7,950.76 | ||||
| Costo Directo | $185,109.03 |