| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020102 | Excavacion 0-2m manual material heterogeneo | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADMT | Cuadrilla Mvto de tierra | jor | 0.112110 | $107,037.00 | $11,999.92 |
| Suma de Mano de Obra | $11,999.92 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MOTOB01 | Motobomba | gl | 0.250000 | $1,100.00 | $275.00 |
| Suma de Equipo | $275.00 | ||||
| Auxiliar | |||||
| TRLOC | Transporte local | m3 | 1.300000 | $5,000.00 | $6,500.00 |
| Suma de Auxiliar | $6,500.00 | ||||
| Concepto | |||||
| 160304 | Entibado temporal | m2 | 0.200000 | $9,298.00 | $1,859.60 |
| 020402 | Cargue (Paleros)-transp-botada. | m3 | 1.300000 | $27,048.00 | $35,162.40 |
| Suma de Concepto | $37,022.00 | ||||
| Costo Directo | $55,796.92 |