| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130110 | Acometida 4#6 tubo emt 2. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CABLECOBT06 | Cable cobre THHN/THWN 6 awg | ml | 4.000000 | $5,421.00 | $21,684.00 |
| CINTAS23 | Cinta scotch 23 18mmx9.1 m | un | 0.010000 | $35,862.00 | $358.62 |
| CINTAS33 | Cinta sctch 33 19mmx8m | un | 0.010000 | $13,952.00 | $139.52 |
| GRA2 | Grapa galvanizada de 2" | un | 1.000000 | $1,048.00 | $1,048.00 |
| CUREMT2 | Curva EMT 2" | un | 0.100000 | $8,344.00 | $834.40 |
| TUBOCONDEM5 | Tubo conduit galvanizado emt 2" | ml | 1.000000 | $34,241.00 | $34,241.00 |
| PERNO | Perno ¼x2 pistola alta veloc | un | 0.700000 | $299.00 | $209.30 |
| Suma de Material | $58,514.84 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.021073 | $116,803.00 | $2,461.39 |
| Suma de Mano de Obra | $2,461.39 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $60,976.23 |