| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100209 | Guardaescoba en mortero imperm ½ caña | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SIKA1 | Sika 1 impermeabilizante integral (20 kg) | kg | 0.150000 | $5,429.00 | $814.35 |
| CHAFL1X1 | Chaflan 1x1 | un | 0.400000 | $1,623.00 | $649.20 |
| Suma de Material | $1,463.55 | ||||
| Mano de Obra | |||||
| ZCUADPIS | Cuadrilla Pisos | jor | 0.037500 | $121,896.00 | $4,571.10 |
| Suma de Mano de Obra | $4,571.10 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 0.100000 | $1,000.00 | $100.00 |
| Suma de Auxiliar | $100.00 | ||||
| Concepto | |||||
| 050216 | Mortero 1:4 de revoque | m3 | 0.010000 | $276,729.00 | $2,767.29 |
| Suma de Concepto | $2,767.29 | ||||
| Costo Directo | $8,901.94 |