| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010206 | Tanque curado cilindros 3.05 x 3.05 m | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQR083P-10-20 | Bloque R8 3P no estructural 10x20x40 | un | 10.750000 | $1,120.00 | $12,040.00 |
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 1.551000 | $21,704.00 | $33,662.90 |
| RECEBO | Recebo comun | m3 | 0.100000 | $38,280.00 | $3,828.00 |
| ARENAPEGA | Arena de pega | m3 | 0.001300 | $30,556.00 | $39.72 |
| ARENAREV | Arena de revoque | m3 | 0.024000 | $23,200.00 | $556.80 |
| SIKA1 | Sika 1 impermeabilizante integral (20 kg) | kg | 0.430000 | $5,429.00 | $2,334.47 |
| TUBOPVP01 | Tubo pvc rde 9 de ½" - Pavco | ml | 3.036700 | $2,559.00 | $7,770.92 |
| CODOPVP01 | Codo pvc-p ½ x 90 | un | 0.430000 | $421.00 | $181.03 |
| LLAVEBOC10 | Llave bocamanguera 1/2" | un | 0.107000 | $17,576.00 | $1,880.63 |
| OTRMA | Otros materiales | gl | 0.100000 | $1,000.00 | $100.00 |
| Suma de Material | $62,394.47 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.117700 | $115,595.00 | $13,605.53 |
| Suma de Mano de Obra | $13,605.53 | ||||
| Auxiliar | |||||
| TRZAGR20 | Transporte pétreos | m3 | 0.100000 | $20,571.00 | $2,057.10 |
| Suma de Auxiliar | $2,057.10 | ||||
| Concepto | |||||
| 020407 | Transporte arena de pega | m3 | 0.001300 | $19,800.00 | $25.74 |
| 020406 | Transporte arena de revoque | m3 | 0.024000 | $19,800.00 | $475.20 |
| Suma de Concepto | $500.94 | ||||
| Costo Directo | $78,558.05 |