| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 220107 | Cordon vaciado | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.044118 | $115,595.00 | $5,099.82 |
| Suma de Mano de Obra | $5,099.82 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| FORMALETA | Formaleta | gl | 3.000000 | $1,000.00 | $3,000.00 |
| Suma de Equipo | $3,000.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.154000 | $1,000.00 | $154.00 |
| Suma de Auxiliar | $154.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.067000 | $294,870.00 | $19,756.29 |
| Suma de Concepto | $19,756.29 | ||||
| Costo Directo | $28,010.11 |