| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130111 | Vestida primaria RA2-007 | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GR250 | Grapa terminal prim 250 | un | 3.000000 | $19,481.00 | $58,443.00 |
| TORNIM01 | Tornillo maquina 5/8 x 1/2 | un | 2.000000 | $1,864.00 | $3,728.00 |
| TORNIEM02 | Tornillo ensamble 5/16 | un | 5.000000 | $46.00 | $230.00 |
| AISLAYO | Aislador yo-yo | un | 1.000000 | $6,951.00 | $6,951.00 |
| TIRA1 | Tiranta ANG 2.4mts galv | un | 2.000000 | $24,930.00 | $49,860.00 |
| ESPBA | Espigo barra galv | un | 1.000000 | $24,153.00 | $24,153.00 |
| CORTAC2 | Cortacircuitos 20KA 10KV | un | 3.000000 | $174,720.00 | $524,160.00 |
| PARAR | Pararrayos OB 10KA-10KVPDV-100 | un | 3.000000 | $92,960.00 | $278,880.00 |
| CRUC2 | Cruceta galvanizada 2.4mx3"x1/4" | un | 2.000000 | $105,989.00 | $211,978.00 |
| AISLSUS5 | Aislador suspension #6, clevis, 10000L (52-1) 8235 | un | 6.000000 | $2,016.00 | $12,096.00 |
| VARIO | Varios electricos | un | 0.500000 | $1,318.00 | $659.00 |
| Suma de Material | $1,171,138.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.383142 | $116,803.00 | $44,752.14 |
| Suma de Mano de Obra | $44,752.14 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 6.000000 | $1,000.00 | $6,000.00 |
| Suma de Auxiliar | $6,000.00 | ||||
| Costo Directo | $1,221,890.14 |