| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110215 | Tubo concreto 40 uec. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONCRE09 | Tubo concreto reforzada D=40" L=1.4m cl2 | ml | 1.030000 | $513,672.00 | $529,082.16 |
| ENSAYOT18 | Ensayo de tuberia | gl | 1.000000 | $1,259.00 | $1,259.00 |
| Suma de Material | $530,341.16 | ||||
| Mano de Obra | |||||
| ZCUADURB | Cuadrilla Urbanismo | jor | 0.286590 | $118,357.00 | $33,919.93 |
| Suma de Mano de Obra | $33,919.93 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETR1 | Retroexcavadora | hr | 0.500000 | $70,000.00 | $35,000.00 |
| Suma de Equipo | $35,000.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 4.700000 | $1,000.00 | $4,700.00 |
| Suma de Auxiliar | $4,700.00 | ||||
| Costo Directo | $603,961.09 |