| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130630 | Salida toma trifásico 4H-50A | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOCONDEM1 | Tubo conduit galvanizado emt 1" | ml | 10.000000 | $15,059.00 | $150,590.00 |
| CUREMT1 | Curva EMT 1" | un | 2.000000 | $3,550.00 | $7,100.00 |
| ALAMBRCOB08 | Alambre cobre desnudo 8 awg | ml | 36.000000 | $3,038.00 | $109,368.00 |
| ALAMBRCOB06 | Alambre cobre desnudo 6 awg | ml | 12.000000 | $5,157.00 | $61,884.00 |
| TIRNE | Tiros neumaticos | un | 2.000000 | $2,258.00 | $4,516.00 |
| TOMATRIF02 | Toma trifasico 4H-50A | un | 1.000000 | $82,953.00 | $82,953.00 |
| Suma de Material | $416,411.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.071520 | $116,803.00 | $8,353.75 |
| Suma de Mano de Obra | $8,353.75 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.000000 | $1,000.00 | $1,000.00 |
| Suma de Auxiliar | $1,000.00 | ||||
| Costo Directo | $425,764.75 |