| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 140215 | Curva pvc-db 4" | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CURPVC40 | Curva pvc conduit 4 | un | 1.000000 | $32,352.00 | $32,352.00 |
| VARIO | Varios electricos | un | 2.320000 | $1,318.00 | $3,057.76 |
| SOLDPVC02 | Soldadura pvc (¼) - Pavco | un | 0.020000 | $50,808.00 | $1,016.16 |
| Suma de Material | $36,425.92 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.127714 | $116,803.00 | $14,917.38 |
| Suma de Mano de Obra | $14,917.38 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 0.500000 | $1,000.00 | $500.00 |
| Suma de Auxiliar | $500.00 | ||||
| Costo Directo | $51,843.30 |