| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130701 | Sub-estacion y proyecto de redes | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACOM4 | Acometida concentrica are Cu 90°C 1x8+8 awg 600V | ml | 60.000000 | $7,495.00 | $449,700.00 |
| PUEST | Puesta a tierra | ml | 2.000000 | $95,968.00 | $191,936.00 |
| BRK3X250 | Breaker 3x250 A indust (Chint) | un | 1.000000 | $210,000.00 | $210,000.00 |
| VES033 | Vestida primaria NRA2-033 | un | 2.000000 | $501,462.00 | $1,002,924.00 |
| TABLEROROB70 | Tablero en roble 15mm x 1.22m x 2.44m | un | 1.000000 | $235,304.00 | $235,304.00 |
| PROTE | Proteccion transformador trifilar | un | 1.000000 | $1,177,517.00 | $1,177,517.00 |
| TRANSFT75 | Transformador 3F 7.2 KV 220/127 V 75 KVA | un | 1.000000 | $14,109,962.00 | $14,109,962.00 |
| ACOM6 | Acometida concentrica are Cu 75°C 2x8+8 awg 600V - redonda | ml | 100.000000 | $11,448.00 | $1,144,800.00 |
| POSTECONC12 | Poste concreto alumbrado 12m tipo EPM | un | 1.000000 | $915,132.00 | $915,132.00 |
| VIENPR | Viento prim con N RA6-001 C/CA | un | 1.000000 | $120,221.00 | $120,221.00 |
| VARIO | Varios electricos | un | 50.000000 | $1,318.00 | $65,900.00 |
| Suma de Material | $19,623,396.00 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 2.554278 | $116,803.00 | $298,347.33 |
| Suma de Mano de Obra | $298,347.33 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 50.000000 | $1,000.00 | $50,000.00 |
| Suma de Auxiliar | $50,000.00 | ||||
| Costo Directo | $19,971,743.33 |