| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 050206 | Mortero Grouting 1:3 | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMEGR2 | Cemento gris (50 Kg) Portland tipo I | un | 9.900000 | $21,704.00 | $214,869.60 |
| ARENAPEGA | Arena de pega | m3 | 1.199000 | $30,556.00 | $36,636.64 |
| AGUA | Agua | lt | 150.000000 | $50.00 | $7,500.00 |
| Suma de Material | $259,006.24 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.302780 | $115,595.00 | $34,999.85 |
| Suma de Mano de Obra | $34,999.85 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MEZCLADORA | Mezcladora trompo eléctrica 1.5 sacos / operador | dÃa | 0.200000 | $72,672.00 | $14,534.40 |
| Suma de Equipo | $14,534.40 | ||||
| Concepto | |||||
| 020407 | Transporte arena de pega | m3 | 1.199000 | $19,800.00 | $23,740.20 |
| Suma de Concepto | $23,740.20 | ||||
| Costo Directo | $332,280.70 |