| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 080205 | Impermeabilizacion junta entre losas | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MANTOZE20 | Manto zetal fiber glass P2 | un | 0.015000 | $148,900.00 | $2,233.50 |
| IMPRMC | Imprimante MC-70 | gal | 0.035000 | $3,701.00 | $129.54 |
| PINTUBIT | Pintura bituminosa solarflex (caneca 5 gal) | un | 0.005000 | $229,621.00 | $1,148.11 |
| GAS | Gas (pipeta) | un | 0.002000 | $27,572.00 | $55.14 |
| IGAS | Igas negro - Sika | kg | 0.220000 | $9,078.00 | $1,997.16 |
| Suma de Material | $5,563.44 | ||||
| Mano de Obra | |||||
| ZCUADIMP | Cuadrilla Impermeabilizaciones | jor | 0.025641 | $124,054.00 | $3,180.87 |
| Suma de Mano de Obra | $3,180.87 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.100000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $8,744.31 |