| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 180108 | Rejilla tipo granada 3x2 | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJILL3X2GRA | Rejilla 3" x 2" con granada | un | 1.000000 | $23,135.00 | $23,135.00 |
| SOSCO | Sosco | un | 1.000000 | $1,354.00 | $1,354.00 |
| SIFONST30 | Sifon pvc-s 135º de 4" - pavco | un | 1.000000 | $15,687.00 | $15,687.00 |
| LECHARIO | Lechada rioclaro 1-2 (Corona) | kg | 0.200000 | $2,397.00 | $479.40 |
| CEMBL | Cemento blanco (40 Kg) | un | 0.050000 | $36,900.00 | $1,845.00 |
| Suma de Material | $42,500.40 | ||||
| Mano de Obra | |||||
| ZCUADINS | Cuadrilla Instalaciones | jor | 0.014049 | $116,803.00 | $1,640.97 |
| Suma de Mano de Obra | $1,640.97 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.740000 | $1,000.00 | $1,740.00 |
| Suma de Auxiliar | $1,740.00 | ||||
| Costo Directo | $45,881.37 |