| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 120106 | Desvio colector de concreto 18" | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Concepto | |||||
| 110208 | Tubo concreto 18 uec. | ml | 1.000000 | $107,802.00 | $107,802.00 |
| 020503 | Llenos compactos en arenilla. | m3 | 0.240000 | $56,865.00 | $13,647.60 |
| 110606 | Cilindro mh d=1.20m prefabricado | ml | 0.070000 | $452,096.00 | $31,646.72 |
| 110611 | Cono, cuello, tapa, base Man hole | un | 0.040000 | $626,126.00 | $25,045.04 |
| 020506 | Llenos compactos material excavacion. | m3 | 5.500000 | $23,689.00 | $130,289.50 |
| Suma de Concepto | $308,430.86 | ||||
| Costo Directo | $308,430.86 |