| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070113 | Sobrecimiento bloque 20 | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOQCON20A | Bloque concreto 20x20x40 | un | 13.125000 | $2,200.00 | $28,875.00 |
| Suma de Material | $28,875.00 | ||||
| Mano de Obra | |||||
| ZCUADMAM | Cuadrilla MamposterÃa | jor | 0.072340 | $116,803.00 | $8,449.53 |
| Suma de Mano de Obra | $8,449.53 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.400000 | $1,000.00 | $400.00 |
| Suma de Auxiliar | $400.00 | ||||
| Concepto | |||||
| 050209 | Mortero 1: 4 de pega | m3 | 0.032000 | $285,872.00 | $9,147.90 |
| 050201 | Concreto 2000 psi en obra | m3 | 0.095000 | $261,470.00 | $24,839.65 |
| Suma de Concepto | $33,987.55 | ||||
| Costo Directo | $71,712.08 |