| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 220104 | Cañuela. | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRAE2 | Piedra de entresuelo (sum + transp) | m3 | 0.052500 | $66,125.00 | $3,471.56 |
| Suma de Material | $3,471.56 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.036190 | $115,595.00 | $4,183.38 |
| Suma de Mano de Obra | $4,183.38 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRINT | Transporte interno | glo | 0.500000 | $1,000.00 | $500.00 |
| Suma de Auxiliar | $500.00 | ||||
| Concepto | |||||
| 050203 | Concreto 3000 psi en obra | m3 | 0.042000 | $294,870.00 | $12,384.54 |
| 050209 | Mortero 1: 4 de pega | m3 | 0.007000 | $285,872.00 | $2,001.10 |
| Suma de Concepto | $14,385.64 | ||||
| Costo Directo | $22,540.59 |