| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130114 | Vestida primaria RA3-003 | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AISLSUS5 | Aislador suspension #6, clevis, 10000L (52-1) 8235 | un | 2.000000 | $2,016.00 | $4,032.00 |
| TUWER5 | Tuerca galvanizada ojo 5/8" | un | 2.000000 | $9,693.00 | $19,386.00 |
| GR1/0 | Grapa term prim 1/0 | un | 2.000000 | $23,465.00 | $46,930.00 |
| CONECAL | Conectores aluminio | un | 2.000000 | $3,629.00 | $7,258.00 |
| TORNIE10 | Tornillo espaciador 5/8 x 12 | un | 2.000000 | $8,000.00 | $16,000.00 |
| VARIO | Varios electricos | un | 1.200000 | $1,318.00 | $1,581.60 |
| Suma de Material | $95,187.60 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.224138 | $116,803.00 | $26,179.99 |
| Suma de Mano de Obra | $26,179.99 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 0.500000 | $1,000.00 | $500.00 |
| Suma de Auxiliar | $500.00 | ||||
| Costo Directo | $121,867.59 |