| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130204 | Bajante 2#4/0+1#2/0 galv 3" | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOGA35 | Tubo galvanizado 3" | un | 6.000000 | $51,301.00 | $307,806.00 |
| CABLECOBT02/0 | Cable cobre THHN/THWN 2/0 awg | ml | 11.000000 | $26,488.00 | $291,368.00 |
| CABLECOBT04/0 | Cable cobre THHN/THWN 4/0 awg | ml | 22.000000 | $41,505.00 | $913,110.00 |
| CURPVC30 | Curva pvc conduit 3 | un | 1.000000 | $10,463.00 | $10,463.00 |
| CONECTOR40 | Conector tornillo partido KS-21 3/0 | un | 3.000000 | $35,801.00 | $107,403.00 |
| VARIO | Varios electricos | un | 11.346000 | $1,318.00 | $14,954.03 |
| Suma de Material | $1,645,104.03 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.396552 | $116,803.00 | $46,318.46 |
| Suma de Mano de Obra | $46,318.46 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $1,691,422.49 |