| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ES-34 | TRABES DE ACERO TIPO IPR DE 14"x6-3/4x44.6KG/M. INCLUYE SUMINISTRO, MANO DE OBRA, MONTAJE EN SITIIO, CORTES, SOLDADURAS, UNA CAPA DE PRIMER ANTICORROSIVO, Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. PUOT | kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IR DE 14"X6-3/4X44.6 | PERFIL ESTRUCTURAL IR DE 14"x6-3/4x44.6KG/M. | KG | 1.050000 | $11.00 | $11.55 |
| GAS P/CORTES | GAS P/ CORTES | KG | 0.008614 | $3.96 | $0.03 |
| OXIGENO | OXIGENO | M3 | 0.006000 | $38.50 | $0.23 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.002106 | $31.25 | $0.07 |
| PRIMER INORG. | PRIMER INORGANICO DE ZINC GALVADUR | litro | 0.015000 | $65.00 | $0.98 |
| THINNER | THINNER | LT | 0.020000 | $13.10 | $0.26 |
| SOLDADURA 70E-XX | SOLDADURA 70E-XX | kg | 0.007000 | $25.00 | $0.18 |
| Suma de Material | $13.29 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.005128 | $691.36 | $3.55 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.003333 | $691.36 | $2.30 |
| CUADRILLA 19 | Cuadrilla de pintores(1 OF. PINTOR + 2 AYUDANTES) | Jor. | 0.001667 | $931.18 | $1.55 |
| APLANOS TALLER | MANO DE OBRA DE CALCULISTAS Y DIBUJANTES POR JORNADA DE TRABAJO | jor | 0.000250 | $1,309.84 | $0.33 |
| Suma de Mano de Obra | $7.73 | ||||
| Herramienta | |||||
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.015000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AEQUIPO OXICORTE | EQUIPO DE CORTE OXIGENO-GAS | hora | 0.013880 | $10.10 | $0.14 |
| AAESMERILADORA | ESMERILADORA | hora | 0.028440 | $2.64 | $0.08 |
| ASOLDADORA | Soldadora Miller Mod. S64 | HR | 0.018310 | $16.12 | $0.30 |
| AEQUIPO PINTURA | EQUIPO DE PINTURA IPSA | hora | 0.010000 | $13.12 | $0.13 |
| Suma de Equipo | $0.64 | ||||
| Auxiliar | |||||
| SAND BLAST | sand blast a metal blanco | kg | 1.030000 | $3.47 | $3.57 |
| Suma de Auxiliar | $3.57 | ||||
| Costo Directo | $25.24 |