| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AL-6 | GUARNICION DE CONCRETO f'c 150 kg/cm2 ACABADA CON PINTURA DE ESMALTE COLOR AMARILLO TRANSITO | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALAMBRE REC. | ALAMBRE RECOCIDO | KG | 0.300000 | $10.43 | $3.13 |
| DIESEL | DIESEL | LT | 0.500000 | $5.06 | $2.53 |
| CELOTEX | junta constructiva a base de celotex | M2 | 0.008330 | $72.56 | $0.60 |
| PINTURA P/TRAFICO | CON MICROESFERA | LT | 0.087500 | $90.00 | $7.88 |
| THINNER | THINNER | LT | 0.050000 | $13.10 | $0.66 |
| ESTOPA | ESTOPA | KG | 0.040000 | $35.00 | $1.40 |
| Suma de Material | $16.19 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 2 (1 albañil + 1 peon) | JOR | 0.090909 | $691.38 | $62.85 |
| CUADRILLA 19 | Cuadrilla de pintores(1 OF. PINTOR + 2 AYUDANTES) | Jor. | 0.016667 | $931.18 | $15.52 |
| Suma de Mano de Obra | $78.37 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.063000 | $897.52 | $56.54 |
| BAS -CIMMET | CIMBRA METALICA DE 50 CMS DE ALTURA | ml | 0.030130 | $329.66 | $9.93 |
| Suma de Auxiliar | $66.48 | ||||
| Costo Directo | $161.04 |